Progress report for 6/5/09: Building 1645 1) Power washed roof and cleaned skylights Building 1655 1) Power washed roof and cleaned skylights
Projected work schedule report for 6/8/09 Awaiting door delivery.
Progress report for 6/4/09: Building 1645 1) Completed installation of all Walk Pads. Walk Pad seams that are over membrane laps have been left open so the Duro-Last inspector can check laps. 2) Completed all details and Term Bar on Elevator roof. Counter flashing metal has been left up so the Duro-Last inspector can see Term Bar is installed correctly. 3) Cleaned all construction debris. Building 1655 1) Cleaned all construction debris.
Projected work schedule report for 6/5/09: Building 1655 1) Complete elevator roof. 2) Complete pitch pan filler. 3) Power wash roof and clean skylight lens. Building 1645 1) Power wash roof and clean skylight lens.
|
|
|