Progress report for 6/3/09: Building 1655 1) Completed installation of all Walk Pads. Walk Pads seam that are over membrane laps have been left open so the Duro-Last inspector can check laps. 2 Completed all details and Term Bar except on Elevator roof. Counter Flashing metal has been left up so the Duro-Last inspector can see Term Bar is installed correctly. Building 1645 1) Installed walk pad around center opening.
Projected work schedule report for 6/14/09: Building 1655 1) Complete elevator roof. Building 1645 2) Complete installation of walk pads. 3) Continue detail work.
Progress report for 6/2/09: Building 1655 1) Installed walk pad around roof system and at A/C units of 323, 324, 325, and 326 2) Completed details & term bar over units 327 through 339
Projected work schedule report for 6/3/09: Building 1655 1) Complete all of roof system details except door installations as discussed.
Progress report for 6/1/09: Building 1655 1) Completed term bar over units 327 through 329 upper & lower roofs. 2) Completed details & term bar over units 322 through 326
Projected work schedule report for 6/1/09: Building 1655 1) Complete elevator roof. 2) Install walk pads around center opening and start around A/C's. 3) Continue detail work.
Progress report for 5/29/09: Building 1645 1) Worked on details above elevator shaft Building 1655 2) Installed all membrane over A/C areas over 322 & 323 (All membrane has been installed.) 3) Worked on details over units 321 through 326. 4) Installed T-Bar over units 324 through 326 (lower roofs) 5) Installed T-Bar over units 330 through 331 on wall & gutter (upper roofs)
Projected work schedule report for 6/1/09 Building 1645 1) Complete details and T-Bar on Elevator roof. Building 1655 2) Install T-Bar over units 327 through 329 (upper roofs.) 3) Start detail work over units 322 through 324 (lower roofs)
Progress report for 5/28/09: Building 1645 1) Completed pitch pan filler. 2) Completed installation of A/C platform pans and rubber dampeners. (Metal pans were an additional cost new dampeners were not charged for) Building 1655 3) Installed all membrane over units 322 through 326 except the A/C areas over 322 & 323 4) Completed installation of 2 piece edge metal. 5) Completed details over units 327 through 331.
Projected work schedule report for 5/29/09: Building 1655 1) Complete all installation of membrane. 2) Start details over 322 through 326 3) Install term-bar in gutters on upper roofs over units 327 through 331.
Progress report for 5/27/09: Building 1655 1) Completed installation of Dens-Deck over all units. 2) Started installation of membrane over 323 through 325 Extras: Removed and installed 24 lf of fascia - 2 men 3 hours
Projections for work to be performed on 5/28/09: Building 1655 1) Complete install of membrane over units 323 through 325 2) Continue detail work over units 322 through 326
Progress report for 5/26/09: Building 1655 1) Tear Off roofing material over units 324 through 326. 2) Continued detail work over units 327 through 331. Extras: Replaced 13 sheets of plywood over 323 through 326
Projected work schedule report for 5/27/09: Building 1655 1) Tear Off over units 322 through 324. ( This will complete all tear off ) 2) Inspect and replace plywood as needed. 3) Install membrane along bottom edge over units 324 through 326
Progress report for 5/22/09: Building 1645 1) Completed pitch pans with filler. 2) Completed and secured all skylights. Building 1655 1) Continued detail work over units 327 through 331. 2) Installed pitch pans and filled with foam over units 327 through 331.
Projected work schedule report for 5/26/09 Building 1655 1) Tear-off over units 332 through 326. ( This will complete all tear off work on this building. ) 2) Inspect and replace plywood as needed. 3) Complete detail work over units 327 through 331.
Progress report for 5/21/09: Building 1655 1) Continue details over upper roofs on units 322 through 326 3) Performed detail work on lower roofs of units 327, 328 and 329 4) Installed T-Bar on all upper roof walls 5) Installed T-Bar details in gutter areas over units 322, 323, and 324 6) Installed T-Bar on lower roof walls over units 328, 329, and 330 Building 1645 No significant work performed here today. Extras: None today
Projected work schedule report for 5/22/09 Building 1655 1) Continue details over lower roofs on units 327 through 331 2) Finish elevator roofs (except for t-bar detail) 3) Replace 24 of fascia board at stairway as proposed. 4) Will change out approx 4 sheets of plywood locations not exact yet. 5) No additional tear-off work till Tuesday.
Progress report for 5/20/09: Building 1655 1) Continue details over upper roofs on units 328, 329, 322 through 326 2) Install membrane on units 327, 328, 329, 330, and 331 in the A/C areas. 3) Started details on lower roofs on units 327, and 328 4) Installed T-Bar on upper roofs on units 322, 323 and 324 Extras: Installed safety supports for rotted stair way beams. This was getting dangerous for the crew to use.
Projected work schedule report for 5/21/09 Building 1655 1) Continue details over upper roofs on units 326 through 331 2) Continue details on lower roofs on units 328 through 331 3) Continue T-Bar installation on upper roofs on units 325 through 328
Progress report for 5/19/09: Building 1645 1) Installed field over elevator roof. Satellite dishes were removed and reset (dishes no longer have to be moved). 2) Completed installation of pitch pans. 3) Completed field membrane. Building 1655 1) Installed Dens-Deck over units 330, and 331. 2) Installed membrane over units 327, 328, 329, 330, and 331. 3) Continued details over upper roofs on units 322, 323, 330, and 331 4) Removed and reset satellite dishes over elevator (dishes no longer have to be moved). Extras: Changed out 7 sheets of plywood over units 329, 330 and 331
Projected Work Schedule for 5/20/09 Building 1655 1) Continue details over upper roofs on units 328, 329, 324, and 325 2) Install membrane on units 327, 328, 329, 330, and 331 in the A/C areas. 3) Remove and install new fascia wood at top of stairs. 4) Complete elevator roof. Building 1645 1) Complete membrane over elevator. 2) Seal and secure skylights. 3) Fill pitch pans.
Progress report for 5/18/09: Building 1655 1) Tear off of lower roof decks over units 327, 328, 329 2) Install Dens-Deck over units 327, 328, 329. 3) Started installing T Bar over units 330, 331 upper decks. 4) Started detail work over units 330, 331 upper decks. Extras: Replaced 7 sheets plywood Building 1645 1) Started installing pitch pans.
Projected Work for 5/19/09 Building 1655 1) Tear off of lower roof decks over units 330, 331 2) Install Dens-Deck over units 330, 331 3) Complete elevator roof. Building 1645 1) Finish installing pitch pans. 2) Complete elevator roof.
Progress report for 5/19/09: Building 1645 1) Installed field over elevator roof. Satellite dishes were removed and reset (dishes no longer have to be moved). 2) Completed installation of pitch pans. 3) Completed field membrane. Building 1655 1) Installed Dens-Deck over units 330, and 331. 2) Installed membrane over units 327, 328, 329, 330, and 331. 3) Continued details over upper roofs on units 322, 323, 330, and 331 4) Removed and reset satellite dishes over elevator (dishes no longer have to be moved). Extras: Changed out 7 sheets of plywood over units 329, 330 and 331
Projected Work Schedule for 5/20/09 Building 1655 1) Continue details over upper roofs on units 328, 329, 324, and 325 2) Install membrane on units 327, 328, 329, 330, and 331 in the A/C areas. 3) Remove and install new fascia wood at top of stairs. 4) Complete elevator roof. Building 1645 1) Complete membrane over elevator. 2) Seal and secure skylights. 3) Fill pitch pans.
Progress report for 5/13/09: 1) Installed membrane around 3 skylights. 2) Completed term bar installation. 3) Completed 2 pc edge metal installation. 4) Installation of pipe flashings
Projected work schedule for 5/14/09: 1) Tear off of upper roof decks above units 322, 323, 324, 325 and 326. 2) Inspect deck for bad wood and replace as needed. Projected work schedule for Friday 5/15/09: 1) Tear off of upper roof decks on units 327, 328, 329, 330, and 331 2) Inspect deck for bad wood and replace as needed. 3) Install Dens-Deck on this side of building.
Progress report for 5/12/09: 1) Installed membrane around 8 skylights. 2) Installed term bar in gutters over unit 314, 316, 316 3) Continued detail work, term bar, pipes over units 314, 315 4) Installed 2 piece metal at roof edge approximately 150 lf
Projected work schedule for 5/13/09: 1) Complete term bar on upper and lower roofs. 2) Continue detail work over lower units 311, 312. Hope to complete all detail work except pitch pans. 3) Complete 2 piece metal at roof edge.
Progress report for 5/11/09: 1) Completed heat welding of all membrane laps. 2) Installed term bar in gutters over unit 317 through 320. 3) Continued detail work, term bar, pipes over units 311, 312, 314. 4) Installed membrane flashings on 10 skylights for units 317 through 320
Projected work schedule for 5/12/09: 1) Install term bar on upper decks at gutter areas units 321, 311, 312 2) Continue detail work over lower units 314, 315 & 316. We hope to complete detail work except pitch pans by end of day.
Progress report for 5/8/09 1) Completed membrane installation. 2) Installed term bar in gutters over unit 321. 3) Continued detail work, term bar, pipes over units 317 & 318 4) Roof is water tight for the weekend.
Projected work schedule for 5/11/09: 1) Install term bar on upper decks at gutter areas units 311, 312. 2) Continue detail work over lower units 311, 312, 314.
Progress report for 5/7/09 1) Completed Dens-Deck installation. 2) Installed membrane over units 321, 311, 312 3) Installed term bar at gutter details over units 317, 318, 319. 4) Continued detail work over units 320, 321.
Projected work schedule for 5/8/09: 1) Install term bar on upper decks at gutter detail areas over units 320, 321, 316. 2) Install Duro-Last membrane to covered deck area over units 311 through 312 3) Continue detail work over lower units 311, 312, 314.
Progress report for 5/6/09 1) Tore off lower level roofing material over units 311 through 312. This completes tear off for Building 1645. 2) Installed membrane over units 314, 315, and 316 3) Could not install Dens-Deck to remainder of roof as the city inspector did not show up again. 4) Completed term bar installation on all upper decks except in gutter areas. 5) Continued detail work. Extras: Replaced bad plywood 5 sheets - 1 sheet around A/C unit @ 316 and 4 sheets in the field over units 310 through 312.
Projected work schedule for 5/7/09: 1) Install term bar on upper decks at gutter areas. 2) Install Dens-Deck to plywood decking over units 311 through 312 3) Install Duro-Last membrane to covered deck area over units 311 through 312 4) Continue detail work over lower units. 5) Will find out what occurred with the antenna cable as reported by Jake.
Progress report for 5/5/09 We are running a bit behind now due to plywood replacement, Duro-Last inspector changes and the work on the boiler sections of the two roofs at once. We are probably 3 days off schedule now meaning that 1645 roof will probably not complete with major install work till next Wednesday. We of course will be working both roofs at once by then, but there are a lot of small details that will need attention on the 1645 roof before we can be off of it. This time extension does NOT include the door installs of course that is separate. 1) Tore off Lower level roofing material over units 314, 315 through 316. 2) Completed Dens-Deck installation on same area. 3) Continued detail and term bar installation over 317 thru 321 upper and lower areas. Extras: Replaced bad plywood 7 sheets over 314 through 316
Projected work schedule for 5/6/09: 1) Tear off over units 311 through 312. This will complete the tear off of this building. Completion of Inspection of lower level roofs over units 314 through 316. 2) Install Dens-Deck to plywood decking over units 311 thru 312 3) Install Duro-Last membrane to covered deck area over units 314 through 316
Progress report for 5/4/09 1) Tore off around and under Boilers on both buildings worked with Mechanical contractor to have both areas worked today. 2) Built curbs and enclosed on both buildings. 3) Boiler Co. reset and completed connections. 4) Continued detail work over all units of the 1645 building.
Projected work schedule for 5-5-09: 1) Will tear off existing roof system over units 311 312 - 314 2) Will install Dens-Deck to plywood decking over units 311 312 - 314 3) Will continue Duro-Last membrane install to covered deck areas. Emergency Contacts for Roof Replacement Project
5/01/09,
CIS has covered everything as well as possible against this freak rain predicted for tonight. CIS has made sure that everything is watertight, but as they are in the middle of production, leaking during a rain is possible. If anything should occur leak-wise tonight or tomorrow, please contact John Wolf at CIS immediately at (949) 701-8288. If you cannot reach John, please contact Bill Baley at (949) 701-8988 We are confident all will be well - but again we just want to be sure we have you covered.
Progress report for 4/30/09 1) Completed Dens-Deck installation on large lower level roofs over units 319 thru 321. 2) Started installation of membrane on large lower level roofs over units 319 thru 321 field only, we still need to complete details at A/C units here. 3) Began detail work on upper levels and began gutter installations over units 314 and 315. 4) City inspector showed today and agreed to let us continue at our pace as he was pleased we were vigilant about removing bad decking as required. Hopefully his inspections will no longer be an issue for us. 5) We are not removing any more material as rain is forecasted for Saturday (whod have guessed?). Extras: None to report today. Projected work schedule for 5-1-09: 1) Will continue membrane installation over deck areas we started today. 2) Will complete membrane install at A/C units on lower deck areas of 319-321. 3) Will continue gutter installations on 314 through 319. 4) Continue Duro-Last membrane install to covered deck areas in preparation of weekend rain.
Progress report for 4/29/09 1) Tore off Lower level roofing material over units 317 thru 321. 2) Completed Dens-Deck installation on upper level roofs over units 319 thru 321. 3) Installed membrane on upper level roofs over units 311 thru 318 ( approx. 25 squares) field only, we still need to complete wall details. 4) Removed skylight domes and installed plywood then re-installed domes to skylights over units 317 thru 321. 5) City inspector never showed today so we did not receive a deck inspection today as planned. This inspector is causing us quite a bit of slow down. We will discuss with city tomorrow. 6) Covered all open areas with poly for weather protection. Extras: Replaced bad plywood 2 sheets 2 sheets around drain at lower roof level over unit 321 Projected work schedule for 4-30-09: 1) Completion of Inspection of lower level roofs over units 317 thru 321. 2) Install Dens-Deck to plywood decking over units 317 thru 321 3) Continue Duro-Last membrane install to covered deck area.
Progress report for 4/28/09 1) Tore off and had inspected by city (approx. 22 squares) upper level roofs over units 317 thru 321. 2) Installed Dens-Deck insulation to plywood decking on upper level roofs - over units 311 thru 319 (approx. 33 squares). This was also inspected by the city and approved. 3) Installed Duro-Last membrane over unit 315 upper level roof. We had to wait for city inspector before we could start the membrane install. Inspector arrived late (holding up job progress) and was done inspecting at 2:00. He agreed to allow us to cover the installed Dens-Deck going forward without waiting for his inspection as long as the plywood decking was already inspected. 4) Installed polyethylene plastic over all torn-off areas for weather protection just in case no rain forecasted. 5) We notified unit 319 owner in regards to skylight removal in the A.M., they will be there when we open skylight. Units 317 and 318 were not at home, so we will check with them again in the morning. Note: Received e-mail from Debbie in regards to TV. interruption. Apparently this was not our issue, if it was please let me know. Extras: Replaced bad plywood 8 sheets - 1 sheet over unit 317 - 1 ½ sheets over unit 318 - 1 ½ sheets over unit 319 - 3 sheets over unit 320 - 1 sheet over unit 321 4-29-09 work projection 1) We intend to tear-off lower roof level roofing over units 317, 318, 319. 2) Complete Dens-Deck install over all torn-off areas. 3) Continue membrane install on upper level roofs over units 311 thru 316.
|
|
|